Site Checklist

  • Site Address: QX214 St Vincent’s Toowoomba
  • Inspector Name: Johnny lett
  • Inspection Date: 25/02/2026
  • Site Contact on Day: Sharmayne Pearce

PATCH AND PAINT TASKS

  • Introduction to practice manager
  • Address any practice manager concerns
  • Inspect exterior perimeter of practice where applicable
  • Inspect signage for damage
  • Inspect any allocated car parks
  • Check for fire system that may require isolation
  • Check floor coverings for damage
  • Check all doors for correct operation
  • Check all doorstops are functional
    • Install doorstop MRI
  • Inspect walls for damage
    • Repaint walls where necessary
  • Check over joinery units for damage
  • Check inside each cabinet for water leaks
  • Check splash backs for water damage
  • Check all silicone to splash backs, basins, sinks
  • Check soap and hand towel dispenser condition
  • Check for damaged ceiling tiles
    • Six ceiling grid tiles are in dirty condition need replacing above PET corridor entry doors, will source in Brisbane and return with them next week.
  • Check all lights are functioning

PAINTED AREAS

Title Colour
Walls 175 square metres Lexicon half
Ceilings
Doors Multiple frames touched up
Trim 70 lineal metres Lexicon half

PICTURES

Before

After

Comment

Repaint walls in reception waiting room

Before

After

Comment

Repaster hole and paint MRI controller room

Before

After

Comment

Plaster and repaint walls in corridor waiting room

Before

After

Comment

Repaint walls in offices

Before

After

Comment

Repaint walls in stress room and every other room that needs repainting

Before

After

Comment

Touchup aluminium woodlook screens four in total

Before

After

Comment

Repaint door frames

Before

After

Comment

Repaint more door frames 14 in total

Before

After

Comment

Six ceiling tiles need replacing have Ordered will fit once we have picked them up

Before

After

Comment

Doorstop fitted in MRI room