Site Checklist

  • Site Address: QX109 Bowen Hills
  • Inspector Name: Johnny Lett
  • Inspection Date: 31/03/2026
  • Site Contact on Day:

PATCH AND PAINT TASKS

  • Introduction to practice manager
    • Lee Luong not there any more introduced ourselves to new manager she was not aware we were coming
  • Address any practice manager concerns
    • On second day of painting she did have a concern of the paint smell in the practice one staff member had to go home early so I wedged the back door open to try and get some airflow coming in.
  • Inspect exterior perimeter of practice where applicable
  • Inspect signage for damage
  • Inspect any allocated car parks
  • Check for fire system that may require isolation
    • Remove masking tape around fire sensor left behind from other trades
  • Check floor coverings for damage
  • Check all doors for correct operation
  • Check all doorstops are functional
  • Inspect walls for damage
    • There are three coloured walls in this practice the main one being lexicon half the other too darker grey features walls all of them needed touching up
  • Check over joinery units for damage
    • Tighten up lunchroom sink faucet tap as was very loose and swinging around
  • Check inside each cabinet for water leaks
  • Check splash backs for water damage
  • Check all silicone to splash backs, basins, sinks
  • Check soap and hand towel dispenser condition
  • Check for damaged ceiling tiles
    • CT x-ray ceiling tiles have mould on them not sure why this is requires further investigation
  • Check all lights are functioning

PAINTED AREAS

Title Colour
Walls 160 m² Lexicon half and silver city
Ceilings
Doors 60 m² Lexicon half and silver city
Trim 80 lineal metres Lexicon half

ITEMS THAT COULD IMPROVE PRACTICE APPEARANCE

General cleaning not very satisfactory dust on skirting boards top of picture frames and walls around air-conditioning ducts Actioned
Total: $0.00

PICTURES

Before

After

Comment

Repaint dirty marks off walls in all changing rooms

Before

After

Comment

Re-plaster hole in wall and repaint all of recovery room

Before

After

Comment

Repaint walls in x-ray 1 & 2 including IOS room

Before

After

Comment

Re-plaster and paint all defects and dirty marks in corridors

Before

After

Comment

Repaint white doors where necessary

Before

After

Comment

Repaint grey doors we are necessary

Before

After

Comment

Remove old Paint cans left on site and pallet left by other trades take to rubbish tip

Before

After

Comment

As mentioned I believe the cleaners here are not up to standard compared to other practices. Floor is very dirty and dust sitting on top of pictures frames skirting boards everywhere

Before

After

Comment

Repaint dirty marks on walls

Before

After

Comment

Mould and dust on ceiling in CT room. This was not fixed in this maintenance schedule