QX109 Bowen Hills
Home
/
QX109 Bowen Hills
Edit Site Checklist
Title
*
Site Address
Inspector Name
Inspection Date
Site Contact on Day
Patch and Paint Tasks
Tasks
Action
Task
Notes
1
Done
Note
1
Lee Luong not there any more introduced ourselves to new manager she was not aware we were coming
1
Add Note
2
Done
Note
1
On second day of painting she did have a concern of the paint smell in the practice one staff member had to go home early so I wedged the back door open to try and get some airflow coming in.
1
Add Note
3
Done
Note
1
Add Note
4
Done
Note
1
Add Note
5
Done
Note
1
Add Note
6
Done
Note
1
Remove masking tape around fire sensor left behind from other trades
1
Add Note
7
Done
Note
1
Add Note
8
Done
Note
1
Add Note
9
Done
Note
1
Add Note
10
Done
Note
1
There are three coloured walls in this practice the main one being lexicon half the other too darker grey features walls all of them needed touching up
1
Add Note
11
Done
Note
1
Tighten up lunchroom sink faucet tap as was very loose and swinging around
1
Add Note
12
Done
Note
1
Add Note
13
Done
Note
1
Add Note
14
Done
Note
1
Add Note
15
Done
Note
1
Add Note
16
Done
Note
1
CT x-ray ceiling tiles have mould on them not sure why this is requires further investigation
1
Add Note
17
Done
Note
1
Add Note
1
Done
Note
1
Add Note
Painted Areas
Title
M²
Colour
1
2
3
4
1
Add Item
Cleanliness Rating
Area
Rating
Comment
1
Poor
Good
Excellent
2
Poor
Good
Excellent
3
Poor
Good
Excellent
4
Poor
Good
Excellent
1
Poor
Good
Excellent
Add Item
Items That Could Improve Practice Appearance
Contractor Notes
Contractor Item Note
Cost
Completion
1
General cleaning not very satisfactory dust on skirting boards top of picture frames and walls around air-conditioning ducts
Actioned
Required
1
Actioned
Required
Add Contractor Item Note
Photos
Before
After
Comments
1
Repaint dirty marks off walls in all changing rooms
2
Re-plaster hole in wall and repaint all of recovery room
3
Repaint walls in x-ray 1 & 2 including IOS room
4
Re-plaster and paint all defects and dirty marks in corridors
5
Repaint white doors where necessary
6
Repaint grey doors we are necessary
7
Remove old Paint cans left on site and pallet left by other trades take to rubbish tip
8
As mentioned I believe the cleaners here are not up to standard compared to other practices. Floor is very dirty and dust sitting on top of pictures frames skirting boards everywhere
9
Repaint dirty marks on walls
10
Mould and dust on ceiling in CT room. This was not fixed in this maintenance schedule
1
Add Photo