Edit Site Checklist
Title
*
Site Address
Inspector Name
Inspection Date
Site Contact on Day
Patch and Paint Tasks
Tasks
Action
Task
Notes
1
Done
Note
1
Add Note
2
Done
Note
1
Practice manager requested if we could paint ceiling in x-ray 1 as it has a lot of dirty marks on it and take another look at computer topography entrance door as it does not close properly Kenny has tried to fix this in the past. None of these items were fixed in this maintenance routine
1
Add Note
3
Done
Note
1
Paint fence and concrete at entrance due to old flower box being removed
1
Add Note
4
Done
Note
1
Add Note
5
Done
Note
1
Add Note
6
Done
Note
1
Add Note
7
Done
Note
1
Add Note
8
Done
Note
1
Computed topography door needs attention
1
Add Note
9
Done
Note
1
Add Note
10
Done
Note
1
Paint all walls due to wear and tear
1
Add Note
11
Done
Note
1
Add Note
12
Done
Note
1
Add Note
13
Done
Note
1
Add Note
14
Done
Note
1
Remove old silicon and replace with new in staff toilet shower room
1
Add Note
15
Done
Note
1
Add Note
16
Done
Note
1
X-ray one ceiling tiles are not damaged but very discoloured these were not replaced yet
1
Add Note
17
Done
Note
1
Dimmer switch knobs missing still functional Sourcing replacement knobs
1
Add Note
1
Done
Note
1
Add Note
Painted Areas
Title
M²
Colour
1
2
3
4
1
Add Item
Cleanliness Rating
Area
Rating
Comment
1
Poor
Good
Excellent
2
Poor
Good
Excellent
3
Poor
Good
Excellent
4
Poor
Good
Excellent
1
Poor
Good
Excellent
Add Item
Items That Could Improve Practice Appearance
Contractor Notes
Contractor Item Note
Cost
Completion
1
KC, inspected CT entrance doors and frame require replacement to fix properly separate quote to be provided once shielding requirement's are confirmed
Actioned
Required
1
Actioned
Required
Add Contractor Item Note
Photos
Before
After
Comments
1
Plaster and paint office walls behind reception
2
New silicon around hand basin staff toilet
3
Make good paint to fence and concrete at entrance
4
Repaint all five changing rooms
5
Repaint waiting room
6
Repaint all white door frames
7
Door frame on computer topographyhas been re-screwed apparently no fixing behind wall to hold the weight of door needs further investigation
8
Repaint walls reception
9
Repaint corridors
10
Dim switch knobs on order