Title
*
Site Address
Inspector Name
Inspection Date
Site Contact on Day
Patch and Paint Tasks
Tasks
Action
Task
Notes
1
Done
Note
1
Due to early morning starts I was in and painting when I caught up with Alison this was all familiar as I do remember her from last time
1
Add Note
2
Done
Note
1
Alison was a bit concerned about both sides of staff door entrance in front of building deteriorating due to existing grey lacquer peeling off the original dark green powder coded aluminium We prepped the door and coated it in aerosol lacquer paint which looks night and day better than it did.
1
Add Note
3
Done
Note
1
Add Note
4
Done
Note
1
Cleaned black marks off Queensland x-ray sign front door.
1
Add Note
5
Done
Note
1
Add Note
6
Done
Note
1
Add Note
7
Done
Note
1
Add Note
8
Done
Note
1
Add Note
9
Done
Note
1
Add Note
10
Done
Note
1
Repaint all walls where necessary in (lexicon half) repainted BMD room as well this room was a different colour (antique white )
1
Add Note
11
Done
Note
1
Add Note
12
Done
Note
1
Add Note
13
Done
Note
1
Add Note
14
Done
Note
1
Replace old silicon in unisex toilets x2.
1
Add Note
15
Done
Note
1
Add Note
16
Done
Note
1
Replace two cut tiles in the ceiling due to wiring being rearranged in EOS room.
1
Add Note
17
Done
Note
1
Add Note
1
Done
Note
1
Add Note
Painted Areas
Title
M²
Colour
1
2
3
4
5
1
Add Item
Cleanliness Rating
Area
Rating
Comment
1
Poor
Good
Excellent
Dust behind things that do not get moved regularly i.e. behind furniture and under chairs.
2
Poor
Good
Excellent
Light dust on legs of chairs top of picture frames etc.
3
Poor
Good
Excellent
Cobwebs and lots of dust on air conditioning vents looks like the same as the year before.
4
Poor
Good
Excellent
1
Poor
Good
Excellent
Add Item
Items That Could Improve Practice Appearance
Contractor Notes
Contractor Item Note
Cost
Completion
1
Met Ron the cleaner there early one morning and talked about cobwebs etc. He says he has not been given enough time to achieve all the required cleaning. After talking to Alison Dow she is aware of the problem and has requested a cleaning, team to come in and do a spring clean maybe twice a year but has not succeeded. The practice would definitely benefit from thorough clean and a fresh set of eyes to identify areas others have become complacent with.
Actioned
Required
2
I was quite surprised on the general condition of this practice after repainting it a year ago most things are good i.e. toilet door handles tight ,doorstops still strong joinery all working fine . But the general condition of the painted walls ,doors and frames were quite worn obviously a very busy practice.
Actioned
Required
3
Wall Protection A total of 2 sheets were installed (7 pieces) and 7 Corner guards.
Actioned
Required
1
Actioned
Required
Add Contractor Item Note
Photos
Before
After
Comments
1
Some examples of the cleaning not being done up high.
2
Damage to external corners in all corridors, instead of plastering and repainting corner protection was fitted on 7 of these worst affected areas.
3
Redo silicone on water damaged hand basin in toilets notice how dirty tap faucet was before we cleaned it.
4
Repaint walls and column in centre x-ray workstation.
5
Repaint all walls and lunchroom.
6
Repaint both sides of exterior staff entrance door.
7
Repaint six grey doors in various x-ray rooms.
8
Repaint emergency exit door that leads to staircase.
9
Repaint walls after wiring alteration in EOS room replace ceiling tiles as well.
10
Line walls in laundry tub storage area with wall protection due to damage from trolleys.
11
More wall protection fitted in x-ray room 2 this is one example of seven pieces installed in this practice.
12
Repaint changing rooms due to light scuffing and dirty marks on walls 4 rooms in total.
1
Add Photo