Patch and Paint Tasks
Tasks
Action
Task
Notes
1
Done
Note
1
Day before we started called in and introduced ourselves security pass confirmed. Manager had no concerns.
1
Add Note
2
Done
Note
1
Add Note
3
Done
Note
1
One exterior wall of building under Veranda looking like it would benefit from a coat of paint and small tree seedlings growing out of spouting didn’t get up there but would imagine it could have a clean out
1
Add Note
4
Done
Note
1
Add Note
5
Done
Note
1
Add Note
6
Done
Note
1
Add Note
7
Done
Note
1
Flooring in 3 unisex toilets next to ultrasound rooms looks very dirty and chrome looking steel drainage fittings in floor have lost the shine they now look black.
1
Add Note
8
Done
Note
1
Add Note
9
Done
Note
1
Add Note
10
Done
Note
1
Although this practice was better than some we have done it still needed painting in all high traffic areas.
1
Add Note
11
Done
Note
1
Add Note
12
Done
Note
1
Add Note
13
Done
Note
1
Add Note
14
Done
Note
1
Add Note
15
Done
Note
1
Add Note
16
Done
Note
1
Ultrasound rooms one and four have ceiling tiles removed and temporary air-conditioner exhaust fans due to copper thieves removing parts from exterior air-conditioning units.
1
Add Note
17
Done
Note
1
Add Note
1
Done
Note
1
Add Note
Painted Areas
Title
M²
Colour
1
2
3
4
1
Add Item
Cleanliness Rating
Area
Rating
Comment
1
Poor
Good
Excellent
2
Poor
Good
Excellent
3
Poor
Good
Excellent
4
Poor
Good
Excellent
1
Poor
Good
Excellent
Add Item
Items That Could Improve Practice Appearance
Contractor Notes
Contractor Item Note
Cost
Completion
1
Vinyl flooring seems to be dirty in some areas
Actioned
Required
1
Actioned
Required
Add Contractor Item Note
Photos
Before
After
Comments
1
Replaster and paint holes and wear and tear marks in walls ultrasound rooms 1 2 3 & 4
2
Ultra sound room 4 and waiting room prefinished panels has exposed screw holes. Filled with Cabots wood grain filler
3
Fill holes and repaint x-ray rooms
4
Plaster and repaint CT room
5
Seedlings growing out of spouting on roof. Although I did not get up there as sign on the The Wall says permission is needed from landlord. I would think this was full of leaves and would need cleaning ie water blasting.
6
Photo showing dirty vinyl flooring and blackened flooring waste covers
7
We were going to replace ceiling tiles around temporary AC ducting but we told not to worry on the last day by manager has they shouldn’t be there for much longer
8
Repaint 10 grey doors that were damaged
9
Replace chipped and cracked corner protection
10
Walls under veranda and back entrance ramp would benefit from water blasting as concrete ramp was very slippery when it was wet (raining)
1