Site Checklist

  • Site Address: QX176 Capalaba
  • Inspector Name: Johnny lett
  • Inspection Date: 17/03/2026
  • Site Contact on Day: Kirstyn Reeves

PATCH AND PAINT TASKS

  • Introduction to practice manager
  • Address any practice manager concerns
    • Introduce ourselves and obtain a key & alarm code for early morning starts.
  • Inspect exterior perimeter of practice where applicable
    • Car park walls could do with painting.
  • Inspect signage for damage
  • Inspect any allocated car parks
  • Check for fire system that may require isolation
  • Check floor coverings for damage
  • Check all doors for correct operation
    • Very loose door handle on unisex toilet dismantle lubricate and tighten.
  • Check all doorstops are functional
  • Inspect walls for damage
    • Repaint where necessary.
  • Check over joinery units for damage
  • Check inside each cabinet for water leaks
  • Check splash backs for water damage
  • Check all silicone to splash backs, basins, sinks
  • Check soap and hand towel dispenser condition
  • Check for damaged ceiling tiles
    • Replace two damage ceiling tiles.
  • Check all lights are functioning

PAINTED AREAS

Title Colour
Walls 160 m² Lexicon half
Ceilings
Doors 11 doors Customise grey made on site
Trim 60 lineal metres Lexicon half

ITEMS THAT COULD IMPROVE PRACTICE APPEARANCE

Amy, the practice manager at the time requested that the dirty laundry storage area have some wall protection installed around cubicle as the existing laundry tub has sharp edges and is damaging walls I think laundry tub itself is not satisfactory as it appears to be too small She mentioned wall protection could be installed around the back door entrance as well This would benefit as the delivery of goods is damaging the walls there Actioned
Total: $0.00

PICTURES

Before

After

Comment

Plaster and repaint walls in reception and waiting room

Before

After

Comment

Repaint walls in all corridors

Before

After

Comment

Repaint walls in ultrasound rooms 1 2 & 3

Before

After

Comment

Repaint grey doors 11 in total

Before

After

Comment

Repaint door frames and trim where necessary

Before

After

Comment

Replace ceiling tiles in CT control room

Before

After

Comment

Repaint all changing rooms

Before

After

Comment

Repaint both x-ray room walls

Before

After

Comment

Photo shows exterior car park walls that would benefit from a coat of paint. There is only one wall.

Before

After

Comment

Photo shows a repainted dirty laundry storage area This area needs wall protection installed and possibly a new bigger laundry tub

Before

After

Comment

Example of trolley we could source for the practice with rounded edges and increased capacity over current trolley if wanted.